SOE Building Renovation Timeline - Phase 1

Contact: Michael Napolitan, Facilities Manager
Last modified: July 23, 2014

January 1, 2014 – April 30, 2014

Phase 1 will consist of creating construction access to the south basement mechanical room, removing existing SF-1 in the south basement mechanical room and installing the new steam-to-hot-water heat exchangers, primary and secondary pumps, condensate recovery unit and the new air handler, AHU-6. During the process, SF-4 and all steam heat will remain active in order to serve the building until the end of heating season. Heating hot water piping will be installed in the tunnel, valved and capped for future phases. Chilled water piping will be installed in the tunnel and mechanical room and connected to AHU-6. No occupants will be displaced during phase 1.

SOE Building Renovation Phase 1