The proposed renovation plan concentrates on establishing mechanical infrastructure to address the prioritized needs of the SOE. Phase one architectural, electrical and structural work will be completed to support the proposed mechanical systems upgrade proposed. The infrastructure work includes:

  • Replacing existing heating only air handling units and existing window air conditioning units with new central heating and cooling air handling units.
  • Replacing existing steam fed perimeter heating system with new perimeter heating hot water system with new DDC zone controls.
  • Upgrade existing building DDC control panels and existing pneumatic VAV boxes.
  • Provide new toilet room facilities and associated ventilation system at the south end of the building. 